Installation · Stone-lined drain
Certain:
Drain
Probable:
Possible 1:
Possible 2:
Limestone Qualifier 1:
Hard
Limestone Qualifier 2:
Limestone Percent:
100
Bedrock Qualifier 1:
Bedrock Qualifier 2:
Bedrock Percent:
0
Ceramic Qualifier 1:
Ceramic Qualifier 2:
Ceramic Percent:
0
Mud Qualifier 1:
Mud Qualifier 2:
Mud Percent:
Mudbrick Qualifier 1:
Mudbrick Qualifier 2:
Mudbrick Percent:
Nari Qualifier 1:
Nari Qualifier 2:
Nari Percent:
0
Plaster Qualifier 1:
Plaster Qualifier 2:
Plaster Percent:
0
Earth Qualifier 1:
Earth Qualifier 2:
Earth Percent:
0
Stone Qualifier 1:
Stone Qualifier 2:
Stone Percent:
0
Type:
Linear
Quality 1:
Nearly
Quality 2:
Remarks:
Lining:
None
Greatest Length in meters:
1.2
Greatest width in meters:
0
Smallest width in meters:
0.24
Greatest Height in meters:
0
Lowest Height in meters:
0.34
Orientation (degrees):
45
Remarks:
Goes into W balk
| Location | Top Level | Bottom Level |
|---|---|---|
| 7 | 910.44 | 910.1 |
| Relationship | Related to | Related locus |
|---|---|---|
| Under | Surface | L6L70:007 |
| Under | Earth layer | L6L70:008 |
| Equals | Installation | L6K79:017 |
| Fill Loci | Earth layer | L6L70:010 |
| Over | Earth layer | L6L70:020 |
| Over | Surface | L6L70:023 |
| Sealed agnst by | Surface | L6L70:023 |
| Number | Date | Baskets | Total | Diagnostic | Published |
|---|
| Date | Photo Number | Subject | Photo |
|---|---|---|---|
| 21 July, 2006 | 06L70296 | Progress |
|
| 24 July, 2006 | 06L70305 | Progress |
|
| 26 July, 2006 | 06L70338 | Progress |
|
| 18 July, 2006 | 06L70232 | Progress |
|
| 19 July, 2006 | 06L70254 | Progress |
|
| 21 July, 2006 | 06L70299 | Surface 7 |
|
| 2 July, 2008 | 08L70069 | Progress |
|
| 4 July, 2008 | 08L70117 | Progress |
|
| 10 July, 2008 | 08L70228 | Progress |
|
| 14 July, 2008 | 08L70279 | Progress |
|
| 15 July, 2008 | 08L70305 | Progress |
|
| 16 July, 2008 | 08L70334 | Progress |
|
| 22 July, 2008 | 08L70446 | Progress |
|