Architecture · N-S wall W of wall 3
chert Qualifier 1:
Hard
chert Qualifier 2:
chert Qualifier 3:
chert Percent:
10
Limestone Qualifier 1:
Decayed
Limestone Qualifier 2:
Limesotne Qualifier 3:
Limestone Percent:
90
basalt Qualifier 1:
basalt Qualifier 2:
basalt Qualifier 3:
basalt Percent:
0
nari Qualifier 1:
nari Qualifier 2:
nari Qualifier 3:
nari Percent:
0
mudbrick Qualifier 1:
mudbrick Qualifier 2:
mudbrick Qualifier 3:
mudbrick Percent:
Arch Frags:
0
Fragment Type:
Quarry:
Cobble (6-25 cm) %:
10
Small Boulder (25-50cm) %:
Medium Boulder (50-75cm) %:
65
Large Boulder (75-100cm) %:
0
Very Large Boulder (>1 m) %:
0
Pebble (.2-6 cm) %:
10
Cobble (6-25 cm) %:
90
Cobble (6-25 cm) %:
80
Small Boulder (25-50cm) %:
20
Medium Boulder (50-75cm) %:
0
Large Boulder (75-100cm) %:
0
Very Large Boulder (>1 m) %:
0
Length (upper):
0.0
Length (lower):
0.0
Width (upper):
0.0
Width (lower):
0.0
Depth (upper):
0.0
Depth (lower):
0.0
Unhewn %:
100
Semi-hewn %:
Dressed %:
0
Ashlar %:
0
Bossed %:
0
Upper Width:
0.0
Lower Width:
0.0
Upper Length:
0.0
Lower Length:
0.0
Sketch:
false
Photo:
false
Dry-laid %:
100
Clay %:
0
Mud %:
0
Cement %:
0
Plaster %:
0
Average Thickness:
0.0
Facing:
Unfaced
Color:
Style:
Boulder & Chink
Support:
Free-standing
Tendencies:
Massive wall with large stonnes; possibly load-bearing outer wall
Highest Count:
0
Lowest Count:
5
Random:
false
Highest Count:
0
Lowest Count:
2
Two with Rubble:
Random:
false
Greatest Length in meters:
5.2
Greatest width in meters:
1.5
Smallest width in meters:
0.9
Greatest Height in meters:
2
Lowest Height in meters:
1.5
Orientation (degrees):
20
Dip (degrees):
4
Preservation:
Partial Superstructure: Most
Lean Direction (degrees):
106
Lean Degrees:
8
Top Foundation Level:
914.16
Remarks:
As with Wall 3, it slumps to the E; the slump is most severe just across from Wall 4 & to S; see Wall 7K71:27 for phase B; the wall was slumped approximately 35 cm to E
| Location | Top Level | Bottom Level |
|---|---|---|
| 8 | 913.79 | 0 |
| 13 | 913.83 | 0 |
| 14 | 913.53 | 0 |
| 20 | 913.61 | 911.7 |
| 25 | 913.76 | 0 |
| 31 | 913.97 | 0 |
| Relationship | Related to | Related locus |
|---|---|---|
| Under | Earth layer | A7K72:002 |
| Equals | Wall | A7K61:035 |
| Equals | Wall | A7K71:026 |
| Abutted by | Installation | A7K72:011 |
| Abutted by | Wall | A7K71:027 |
| Abutted by | Wall | A7K71:028 |
| Sealed agnst by | Earth layer | A7K72:002 |
| Sealed agnst by | Earth layer | A7K72:008 |
| Sealed agnst by | Earth layer | A7K72:014 |
| Sealed agnst by | Earth layer | A7K72:015 |
| Number | Date | Baskets | Total | Diagnostic | Published |
|---|
| Date | Photo Number | Subject | Photo |
|---|---|---|---|
| 24 July, 1989 | 89A72111 | E balk removal & stone bin |
|
| 28 July, 1989 | 89A72112 | Progress |
|
| 31 July, 1989 | 89A72113 | E balk removal |
|
| 1 August, 1989 | 89A72114 | Progress |
|
| 2 August, 1989 | 89A72115 | Final |
|
| 2 August, 1989 | 89A72116 | Final |
|
| 2 August, 1989 | 89A72117 | Final |
|
| 5 August, 1989 | 891A72030 | Final |
|
| 18 July, 1989 | 89A72106 | Progress |
|
| 24 July, 1989 | 89A72109 | Progress |
|
| 26 July, 1989 | 897A72021 | Progress |
|
| 26 July, 1989 | 89A72118 | Surfaces with Walls 3 & 6 |
|
| 16 June, 1994 | 94A72057 | Pre-excavation |
|
| 17 June, 1994 | 94A72058 | Progress |
|
| 20 June, 1994 | 94A72059 | Progress |
|
| 21 June, 1994 | 94A72060 | Progress |
|
| 22 June, 1994 | 94A72062 | Progress |
|
| 24 June, 1994 | 94B92246 | Progress |
|
| 27 June, 1994 | 94A72078 | Progress |
|
| 28 June, 1994 | 94A72080 | Progress |
|
| 29 June, 1994 | 94A72081 | Progress |
|
| 30 June, 1994 | 94B91221 | Progress |
|
| 1 July, 1994 | 94153 | Progress |
|
| 4 July, 1994 | 94A72084 | Progress |
|
| 5 July, 1994 | 94A72085 | Progress |
|
| 6 July, 1994 | 94A72086 | Progress |
|
| 7 July, 1994 | 94A72087 | Progress |
|
| 11 July, 1994 | 94A72088 | Progress |
|
| 12 July, 1994 | 94A72089 | Progress |
|
| 21 June, 1994 | 94A72061 | L 15 |
|
| 23 June, 1994 | 94A72063 | Progress |
|
| 11 July, 1989 | 89A72099 | Progress |
|
| 12 July, 1989 | 89A72100 | Progress |
|
| 13 July, 1989 | 89A72101 | Progress |
|
| 14 July, 1989 | 89A72103 | Progress |
|
| 17 July, 1989 | 89A72104 | Progress |
|
| 18 July, 1989 | 81AA72014 | Progress |
|
| 26 July, 1989 | 897A72020 | Progress |
|
| 12 July, 1994 | 94A72090 | Final |
|
| 20 July, 1989 | 89A72107 | Progress |
|
| 20 July, 1989 | 89A72108 | Surf 15 |
|
| 23 June, 1994 | 94P078B | Pottery on surface |
|
| 23 June, 1994 | 94P079 | Pottery on surface |
|