Installation · FT for Wall 21
Certain:
Probable:
Possible 1:
Foundation trench
Possible 2:
Limestone Qualifier 1:
Limestone Qualifier 2:
Limestone Percent:
0
Bedrock Qualifier 1:
Bedrock Qualifier 2:
Bedrock Percent:
0
Ceramic Qualifier 1:
Ceramic Qualifier 2:
Ceramic Percent:
0
Mud Qualifier 1:
Mud Qualifier 2:
Mud Percent:
Mudbrick Qualifier 1:
Mudbrick Qualifier 2:
Mudbrick Percent:
Nari Qualifier 1:
Nari Qualifier 2:
Nari Percent:
0
Plaster Qualifier 1:
Plaster Qualifier 2:
Plaster Percent:
0
Earth Qualifier 1:
None
Earth Qualifier 2:
Earth Percent:
100
Stone Qualifier 1:
Stone Qualifier 2:
Stone Percent:
0
Type:
Linear
Quality 1:
None
Quality 2:
Remarks:
Lining:
None
Greatest Length in meters:
1
Greatest width in meters:
0.79
Smallest width in meters:
0.6
Greatest Height in meters:
0
Lowest Height in meters:
0
Orientation (degrees):
21
Remarks:
Was removed with L 3 so plan is only inferred from Walls 21 & 25; fill was excavated with L 3; measurements are taken from Walls 21 & 25
| Location | Top Level | Bottom Level |
|---|---|---|
| 33 | 913.02 | 0 |
| Relationship | Related to | Related locus |
|---|---|---|
| Under | Wall | H7K12:021 |
| Over | Wall | H7K12:025 |
| Cuts | Earth layer | H7K12:003 |
| Cuts | Wall | H7K12:025 |
| Number | Date | Baskets | Total | Diagnostic | Published |
|---|
| Date | Photo Number | Subject | Photo |
|---|---|---|---|
| 5 August, 1998 | 98H12486 | Final |
|