Locus B.8K00.009

Architecture · S wall of LB building

General Information

Locus Type Architecture
Supervisor B. Reiswig
Designation S wall of LB building
Reason Stones clearly structured as a wall
Top Separation
Bottom Separation
Start Date 3 July, 1996
End Date 11 July, 2008

Interpretation

Function S wall of LB building
Stratigraphy remarks May have been reused slightly in IR2; battered against MB rampart near its crest
Balk
Phase
Stratum

Architecture Description

Material

chert Qualifier 1:

chert Qualifier 2:

chert Qualifier 3:

chert Percent:

0

Limestone Qualifier 1:

Hard

Limestone Qualifier 2:

Limesotne Qualifier 3:

Limestone Percent:

100

basalt Qualifier 1:

basalt Qualifier 2:

basalt Qualifier 3:

basalt Percent:

0

nari Qualifier 1:

nari Qualifier 2:

nari Qualifier 3:

nari Percent:

0

mudbrick Qualifier 1:

mudbrick Qualifier 2:

mudbrick Qualifier 3:

mudbrick Percent:

Arch Frags:

0

Fragment Type:

Quarry:

Wall Stones

Cobble (6-25 cm) %:

10

Small Boulder (25-50cm) %:

Medium Boulder (50-75cm) %:

0

Large Boulder (75-100cm) %:

0

Very Large Boulder (>1 m) %:

0

Chinkstones

Pebble (.2-6 cm) %:

0

Cobble (6-25 cm) %:

100

Fillstones: (in Rubble-filled Construction)

Cobble (6-25 cm) %:

0

Small Boulder (25-50cm) %:

0

Medium Boulder (50-75cm) %:

0

Large Boulder (75-100cm) %:

0

Very Large Boulder (>1 m) %:

0

Brick

Length (upper):

0.0

Length (lower):

0.0

Width (upper):

0.0

Width (lower):

0.0

Depth (upper):

0.0

Depth (lower):

0.0

Dressing: (Stone Only)

Unhewn %:

100

Semi-hewn %:

Dressed %:

0

Ashlar %:

0

Bossed %:

0

Tooling (Stone Only)

Upper Width:

0.0

Lower Width:

0.0

Upper Length:

0.0

Lower Length:

0.0

Sketch:

false

Photo:

false

Mortar

Dry-laid %:

100

Clay %:

0

Mud %:

0

Cement %:

0

Plaster %:

0

Average Thickness:

0.0

Facing

Facing:

Unfaced

Color:

Construction

Style:

Boulder & Chink

Support:

Battered

Tendencies:

Courses

Highest Count:

14

Lowest Count:

12

Random:

false

Rows

Highest Count:

4

Lowest Count:

3

Two with Rubble:

Random:

false

Measurements

Greatest Length in meters:

3.2

Greatest width in meters:

0

Smallest width in meters:

1.3

Greatest Height in meters:

3.5

Lowest Height in meters:

2.5

Orientation (degrees):

108

Dip (degrees):

0

Preservation

Preservation:

Partial Superstructure: Most

Lean Direction (degrees):

0

Lean Degrees:

0

Top Foundation Level:

Remarks

Remarks:

No sign of beams for first story; no windows

Levels

Location Top Level Bottom Level
21 912.58 0
28 912.92 0
29 912.52 0
35 913.11 0

Stratigraphy

Relationship Related to Related locus
Sealed agnst by Earth layer B8K00:024
Sealed agnst by Earth layer B8K00:032
Sealed agnst by Earth layer B8K00:033
Under Earth layer B8K00:003
Sealed agnst by Surface B8K00:011
Sealed agnst by Earth layer B8K00:016
Sealed agnst by Earth layer B8K00:017
Sealed agnst by Pit B8K00:015
Bonded to Wall B8K00:014
Sealed agnst by Earth layer B8K00:007
Sealed agnst by Earth layer B8K00:019
Sealed agnst by Earth layer B8K00:008

Pails

Number Date Baskets Total Diagnostic Published

Photos

Date Photo Number Subject Photo
11 July, 1996 96A68016 Progress
3 July, 1996 96B00138 Progress
10 July, 1996 96B00143 Progress
10 July, 1996 96K01401 Progress
10 July, 1996 96K01402 Progress
29 June, 1998 98B00014 Progress
30 June, 1998 98B00034 Progress
7 July, 1998 98B00118 Progress
8 July, 1998 98B00139 Progress
23 July, 1998 98B00328 Progress
31 July, 1998 98B00445 Progress
1 July, 1998 98B00049 Progress
2 July, 1998 98B00064 Progress
9 July, 1998 98B00153 Progress
10 July, 1998 98B00171 Progress
13 July, 1998 98B00190 Progress
14 July, 1998 98B00202 Progress
30 July, 1998 98B00421 Progress
26 June, 2000 00B00012 Pre-excavation
26 June, 2000 00B00012 Pre-excavation
27 June, 2000 00B00026 Progress
27 June, 2000 00B00026 Progress
28 June, 2000 00B00045 Progress
28 June, 2000 00B00045 Progress
29 June, 2000 00B00072 Progress
29 June, 2000 00B00072 Progress
30 June, 2000 00B00092 Progress
30 June, 2000 00B00092 Progress
3 July, 2000 00B00114 Progress
3 July, 2000 00B00114 Progress
6 July, 2000 00B00161 Progress
6 July, 2000 00B00161 Progress
7 July, 2000 00B00187 Progress
7 July, 2000 00B00187 Progress
10 July, 2000 00B00214 Progress
10 July, 2000 00B00214 Progress
11 July, 2000 00B00233 Progress
11 July, 2000 00B00233 Progress
12 July, 2000 00B00256 Progress
12 July, 2000 00B00256 Progress
13 July, 2000 00B00277 Progress
13 July, 2000 00B00277 Progress
14 July, 2000 00B00302 Progress
14 July, 2000 00B00302 Progress
18 July, 2000 00B00344 Progress
18 July, 2000 00B00344 Progress
17 July, 1996 96B00151 Progress
15 July, 1996 96B00149 Progress
16 July, 1996 96B00150 Progress
4 July, 1996 96B00139 Progress
5 July, 1996 96B00140 Progress
8 July, 1996 96B00141 Progress
9 July, 1996 96B00142 Progress
11 July, 1996 96B00147 Progress
11 July, 1996 96B00146 Progress
18 July, 1996 96B00152 Progress
19 July, 1996 96B00153 Progress & L 17
24 July, 1996 96B00156 Progress
26 July, 1996 96B00157 Cobble floor
26 July, 1996 96B00158 Wall 14
22 July, 1996 96B00154 L.14
2 July, 2008 08B00073 Progress
3 July, 2008 08B00097 Progress
4 July, 2008 08B00126 Progress
7 July, 2008 08B00149 Progress
29 July, 2008 08B00619 Final: LB Building SW part
29 July, 2008 08B00617 Final: LB building W part
29 July, 2008 08B00618 Final: LB building W part 2