Locus B.7J89.009

Architecture · E-W wall separating Early Iron 1 Houses A & B

General Information

Locus Type Architecture
Supervisor D. Holloway
Designation E-W wall separating Early Iron 1 Houses A & B
Reason Line of stones
Top Separation Very Clear
Bottom Separation Very Clear
Start Date 11 July, 1984
End Date 21 July, 1994

Interpretation

Function E and W casemate wall with walls 11, 22 and 27 of room. A defense wall of some type. 1994: Wall 9 was a connecting wall between the two parallel walls thus forming a casemate wall system.
Stratigraphy remarks Earliest phase found this season. Bonds with 11. After its disuse, through destruction or whatever, appears to be ignored or forgotten. In later loci walls 9 may have been robbed out. Appears to connect with 22.Tumble in 8 appears to come, partially at least, from 9: the six-sided worked stones may have been 9's facing. In 1989 season, determined to be part of casemate room (in wall) bounded also by walls 22 (on north), 11 (E) and 27 (S). Tumble in L.29, 30 and 31 may come partially from this wall. 1994: Wall 9 (at the east end) was founded at the same level as wall 11.
Balk
Phase
Stratum

Architecture Description

Material

chert Qualifier 1:

chert Qualifier 2:

chert Qualifier 3:

chert Percent:

0

Limestone Qualifier 1:

Hard

Limestone Qualifier 2:

Limesotne Qualifier 3:

Limestone Percent:

100

basalt Qualifier 1:

basalt Qualifier 2:

basalt Qualifier 3:

basalt Percent:

0

nari Qualifier 1:

nari Qualifier 2:

nari Qualifier 3:

nari Percent:

0

mudbrick Qualifier 1:

mudbrick Qualifier 2:

mudbrick Qualifier 3:

mudbrick Percent:

Arch Frags:

0

Fragment Type:

Quarry:

Wall Stones

Cobble (6-25 cm) %:

40

Small Boulder (25-50cm) %:

Medium Boulder (50-75cm) %:

0

Large Boulder (75-100cm) %:

0

Very Large Boulder (>1 m) %:

0

Chinkstones

Pebble (.2-6 cm) %:

40

Cobble (6-25 cm) %:

60

Fillstones: (in Rubble-filled Construction)

Cobble (6-25 cm) %:

0

Small Boulder (25-50cm) %:

0

Medium Boulder (50-75cm) %:

0

Large Boulder (75-100cm) %:

0

Very Large Boulder (>1 m) %:

0

Brick

Length (upper):

0.0

Length (lower):

0.0

Width (upper):

0.0

Width (lower):

0.0

Depth (upper):

0.0

Depth (lower):

0.0

Dressing: (Stone Only)

Unhewn %:

100

Semi-hewn %:

Dressed %:

0

Ashlar %:

0

Bossed %:

0

Tooling (Stone Only)

Upper Width:

0.0

Lower Width:

0.0

Upper Length:

0.0

Lower Length:

0.0

Sketch:

false

Photo:

false

Mortar

Dry-laid %:

100

Clay %:

0

Mud %:

0

Cement %:

0

Plaster %:

0

Average Thickness:

0.0

Facing

Facing:

Unfaced

Color:

Construction

Style:

Boulder & Chink

Support:

Free-standing

Tendencies:

Tight fitting stones

Courses

Highest Count:

Lowest Count:

Random:

false

Rows

Highest Count:

3

Lowest Count:

2

Two with Rubble:

Random:

false

Measurements

Greatest Length in meters:

2.7

Greatest width in meters:

1

Smallest width in meters:

0.93

Greatest Height in meters:

2.1

Lowest Height in meters:

Orientation (degrees):

115

Dip (degrees):

0

Preservation

Preservation:

Partial Superstructure: Half

Lean Direction (degrees):

0

Lean Degrees:

0

Top Foundation Level:

Remarks

Remarks:

12 courses preserved above Surf 33; bottom level was only exposed in a probe

Levels

Location Top Level Bottom Level
2 913.08 0
8 913.48 911.42
9 913.48
10 913.96 911.45
11 913.51 912.91

Stratigraphy

Relationship Related to Related locus
Under Earth layer B7J89:001
Under Earth layer B7J89:002
Under Earth layer B7J89:008
Bonded to Wall B7J89:011
Abuts Wall B7J89:022
Sealed agnst by Earth layer B7J89:029
Sealed agnst by Earth layer B7J89:030
Sealed agnst by Earth layer B7J89:031
Sealed agnst by Earth layer B7J89:033
Equals Wall B7J99:005

Pails

Number Date Baskets Total Diagnostic Published

Photos

Date Photo Number Subject Photo
23 July, 1984 84B89358 Progress
25 July, 1984 84B89406 Progress
26 July, 1984 84B89434 Progress
23 July, 1984 84A51368 Progress
27 July, 1984 84B89453 Progress
30 July, 1984 84B89486 Progress
31 July, 1984 84B89526 Progress
1 August, 1984 84B89544 Progress
11 July, 1984 84B89186 Progress
12 July, 1984 84B89207 Progress
13 July, 1984 84B89225 Progress
16 July, 1984 84B89246 Progress
17 July, 1984 84B89268 Progress
20 July, 1984 84B89335 Progress
24 July, 1992 92B89220 Final from S
24 July, 1992 92B89-382 Final from S
13 July, 1994 94B89176 Pre-excavation
14 July, 1994 94B89177 Progress
15 July, 1994 94B89178 Progress
19 July, 1984 84B89318 Progress
18 July, 1984 8411-0218 Progress
4 August, 1989 789B89041 Closing shot Wall 9
4 August, 1989 89B89547 Final Wall 22
27 June, 1989 89B89177 Progress
28 June, 1989 89B89178 Progress
29 June, 1989 89B89179 Progress
3 July, 1989 89B89181 Progress
11 July, 1989 89B89192 Progress
12 July, 1989 89B89193 Progress
13 July, 1989 89B89195 Progress
14 July, 1989 89B89196 Progress
4 July, 1989 89B89182 Progress
5 July, 1989 89B89185 Progress
17 July, 1989 89B89197 Progress
18 July, 1989 89B89198 Progress
7 July, 1989 89B89189 Progress
7 July, 1989 89B89190 Storejars
10 July, 1989 89B89191 Progress
19 July, 1989 89B89199 Progress
20 July, 1989 89B89200 Progress
24 July, 1989 89B89201 Progress
27 July, 1989 89B89206 Progress
28 July, 1989 89B89207 Progress
31 July, 1989 89B89208 Progress
1 August, 1989 89B89209 Progress
1 August, 1989 89B89210 Pithoi in situ
1 August, 1989 89B89211 Pithoi in situ
30 June, 1989 89B89180 Progress
6 July, 1989 891B89012 Progress
6 July, 1989 891B89012 Progress
1 August, 1989 89B89212 Pithoi in situ
2 August, 1989 89B89213 Progress
4 August, 1989 89B89214 Room
19 June, 1992 92B89195 Progress
24 June, 1992 92B89197 Progress