Locus A.7K42.046

Installation · Possible bin

General Information

Locus Type Installation
Supervisor D. Herr
Designation Possible bin
Reason Semi-circle (?) of stones, going down farther than expected
Top Separation
Bottom Separation
Start Date 6 July, 1992
End Date 31 July, 1992

Interpretation

Function Possible bin
Stratigraphy remarks Filled by L 47
Balk
Phase
Stratum

Installation Description

Type

Certain:

Probable:

Bin

Possible 1:

Possible 2:

Material

Limestone Qualifier 1:

Limestone Qualifier 2:

Limestone Percent:

Bedrock Qualifier 1:

Bedrock Qualifier 2:

Bedrock Percent:

Ceramic Qualifier 1:

Ceramic Qualifier 2:

Ceramic Percent:

0

Mud Qualifier 1:

Mud Qualifier 2:

Mud Percent:

Mudbrick Qualifier 1:

Mudbrick Qualifier 2:

Mudbrick Percent:

Nari Qualifier 1:

Nari Qualifier 2:

Nari Percent:

0

Plaster Qualifier 1:

Plaster Qualifier 2:

Plaster Percent:

0

Earth Qualifier 1:

Earth Qualifier 2:

Earth Percent:

0

Stone Qualifier 1:

None

Stone Qualifier 2:

Stone Percent:

100

Plan

Type:

Semi-circular

Quality 1:

None

Quality 2:

Remarks:

Lining

Lining:

None

Measurements

Greatest Length in meters:

1

Greatest width in meters:

0.75

Smallest width in meters:

0

Greatest Height in meters:

0

Lowest Height in meters:

0

Orientation (degrees):

0

Remarks

Remarks:

If this is a semi-circle, only 1/2 is present; since the bottom of the bin was not removed, bottom levels were not taken

Supplements

Additional descriptions recorded later as the locus was further excavated.

Supplement 1

Levels

Location Top Level Bottom Level
31 912.68 912.12

Stratigraphy

Relationship Related to Related locus
Under Earth layer A7K42:039
Fill Loci Earth layer A7K42:047
Sealed agnst by Earth layer A7K42:047
Sealed agnst by Earth layer A7K42:044
Sealed agnst by Earth layer A7K42:051

Pails

Number Date Baskets Total Diagnostic Published

Photos

Date Photo Number Subject Photo
10 July, 1992 92A42042 Progress
14 July, 1992 92A42044 Progress
13 July, 1992 92A42043 Progress